ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

>> Home   >> Electrical-Photos   >> Classifieds   >> Subscribe to Newsletter   >> Store  
 

Featured:

 Electrical
 Clearance

 *
 Tools
 *

 Books

 *

 Test Equipment

 

Recent Gallery Topics:
What in Tarnation?
What in Tarnation?
by timmp, September 10
Plumber meets Electrician
Plumber meets Electrician
by timmp, September 10
Who's Online Now
0 members (), 1,419 guests, and 13 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#183146 12/28/08 03:08 PM
Joined: Aug 2007
Posts: 853
L
leland Offline OP
Member
I had a discussion the other day with my office, I feel weather tight would meet the code. (existing install is Cls2-div1).
Coal power plant, dock side open conveyer for unloading the barge, Only a shroud over the belt.
My scope: Fire alarm pull stations,120V AC onthe outside railing,notification only to control room. Deluge is manual operation.
The railing is 8' away from the conveyer system,in the wide open air,along the river. All conduit is threaded rigid.
I feel weather tight would be enough.

Work Gear for Electricians and the Trades

Workgear for Electricians

leland #183155 12/28/08 04:26 PM
Joined: Jan 2005
Posts: 5,485
Likes: 4
Cat Servant
Member
For the most part, you're correct. There are two situations that bear considering, though:
1) Where there are moving parts. For example, you don't want dust to get within a breaker, and prevent it from operating. There you would be looking for a dust-tight enclosure; and,
2) Where heat is generated. Motors and light fixtures must remain cool enough that they do not ignite the dusts ... even when they are buried in the dust.